Pursat Province: The Stung Pursat 1 Hydropower Project (80 MW), which closed its water storage gate on June 4, 2026, has reached more than 50% water storage as of September 30, 2026, and is ready to release power for temporary operation at the end of October 2026!

Valuable benefits for citizens:
*Increase clean, affordable electricity sources to serve the national grid.
*Help prevent flooding in Pursat City and prepare to irrigate more than 20,000 hectares of agricultural land.
*Create a new natural tourism area, with a paved road around the floodplain, creating jobs and a kimchi factory for export.

A major step towards clean electricity generation and sustainable development! .
Source: Pursat Provincial Governor’s official page