Phnom Penh: A spokesperson for the Ministry of Public Works and Transport said that according to the plan, the Bassac Chak Angre Krom-Prek Pra River crossing bridge will be connected by the end of 2026, with the left side (currently 10 meters left) planned to be connected in October 2026 and the right side to be connected in mid-December 2026.
He said that the construction of the Bassac Chak Angre Krom-Prek Pra River crossing bridge project has been completed by 81.40% as of the end of July 2026 (faster than planned).

It should be noted that the Chak Angre Krom-Prek Pra Bridge was inaugurated on the morning of February 19, 2024, under the chairmanship of Samdech Techo Hun Sen, Prime Minister, and Mr. Wang Wentian, former Chinese Ambassador to Cambodia.
According to the calendar, the construction process is not slower than the planned work program, and is ready to be completed by the end of 2027.